Open items · Burnstead review

TC-20 Open Items Sat, Sep 19, 2026

Running list of open items for Burnstead, for close-out before the walkthrough on 2026-10-02.

Burnstead Job 3520
Lot #20 at Tibbetts Crossing
Closing 2026-10-20
Issued 2026-09-13

AK offline walkthroughT-18

2026-10-0213 days out

Burnstead walkthroughT-7

2026-10-1324 days out

Final checkT-1

2026-10-1930 days out

ClosingT-0

2026-10-2031 days out · 11:30 AM – 2:00 PM

All P0 and P1 items must be complete by the walkthrough on 2026-10-02.

9 of 13 items on this list are P0 or P1. Anything still open at that walkthrough goes into the closing documents as a we-owe with a named install date.

This is the running list of open items on TC-20, kept in one place so nothing has to be reconstructed from email threads. Each row names where the item is, what action is required, and who it sits with.

The request is that these are worked and closed before the walkthrough on 2026-10-02, ahead of the 2026-10-20 closing. Where an item cannot be completed before then, a we-owe in the closing documents naming the work and an agreed install date works equally well.

The list updates in place; the issue date in the corner is the version. Replies go on the existing email thread.

Process

01
IDPriorityIssueAreaAction requiredStatus
T-099P0Confirm 10/20 Final Closing DateSchedule10/20 completion date with two to three weeks of buffer time to fix all issue. Refer to the above dates.FIXED

Finish

02
IDPriorityIssueAreaAction requiredStatus
T-059P0Patio soffit stain — second application worse than the firstExterior — covered patioUpdate: Met with Chris on Thursday. 1st stain application just started 1PM, 9/17. Will check when its done? One coat or two coat based on if imperfections still visible. Another stain application does not appear likely to resolve the underlying issue, It is not going to fix with Third stain application. It was pressure washed, sanded and apparently water based stain was done. Replace the board, restain oil based stain. https://www.icloud.com/sharedalbum/#D1fv3ffmrCcJ4zbbTjKLsBL8rhQCAEQARogmmJZEOVh9oAgV-UQoa03zbE413FgEe3DMN7_AkMaKsgIN PROGRESS
T-067P3Replace Bed2-Bed3 Door hardware with privacy lock handleBed 2 / Bed 3 / bathReplace the door hardware with privacy lock for Bed 2-3VERIFY ON SITE

HVAC

03
IDPriorityIssueAreaAction requiredStatus
T-001P0Furnace and control below specification, both floors. Replace with Stage-2 Furnace.Mechanical — both systemsUpdate: 9/18 Furnace being installed. Two-stage furnaces on both floors with the matched Bryant control, one brand end to end. Either completed before the house is finished, or documented as a we-owe in the closing documents naming the AHRI combination, the two-stage furnace, the matched Bryant control and agreed install dates, inside a three-month window.IN PROGRESS
T-002P0Honeywell T6 Pro installed; spec calls Bryant A180277-Replace controller with ecobee for Bryant Smart Thermostat - EB-STATE6IBR-01Mechanical — both systemsTwo-stage furnaces on both floors with the matched Bryant control, one brand end to end. Replace controller with ecobee for Bryant Smart Thermostat - EB-STATE6IBR-01IN PROGRESS
T-003P1Heat pump 8.5 HSPF2 against specified 11 HSPFExterior mechanicalNo replacement required for Outdoor units.FIXED

Low voltage

01
IDPriorityIssueAreaAction requiredStatus
T-117P0Security System Install per SpecsPer Specs - Security System: Exterior doors, motion sensors, (2) key pads. Pg 9OPEN

Exterior

01
IDPriorityIssueAreaAction requiredStatus
T-093P1Schedule Landscaping plan discussionLot / siteSchedule meeting with Burnstead landscaping designer. Met Dave 9/17. Finalizing draft in progress.IN PROGRESS

Electrical

04
IDPriorityIssueAreaAction requiredStatus
T-019P1Sauna circuit — Install external disconnect and j-box for 250/120V per codeExterior — sauna padChecked 9/18 - Prewire with non-mettalic box. No disconnect. Per conversation with Leo, it was advised J-Box with external disconnect. CO says prewire only, didn't verify the wording in April. Install J-box, external disconnect per Code for both the 240V run and the separate 110V lighting feed terminate at the intended pad location.OPEN
T-015P1Per CO - Under-stairs rack closet exhaust fan thermostatic controlUnder-stairs storage / equipment closet — main floorPer CO - Install a line-voltage thermostat or equivalent temperature controller on the fan circuit with a configurable setpoint, or swap to a sensor-equipped fan. Without automatic trigger the fan will not run on heat and the equipment in the closet sits unventilated.VERIFY ON SITE
T-016P2Per CO - Three stair lights on photocell — verify photocell functionEntry / foyer — exterior stairsConfirm all three prewires are at the correct stair locations, the photocell is installed and wired to the three-light circuit, it is mounted unshaded by overhang or soffit, and it passes a cover-and-uncover test in daylight.VERIFY ON SITE
T-018P2Five exterior flood lights — junction fixtures missingExteriorInstall metal octagon junction box for the lightVERIFY ON SITE

Appliances

01
IDPriorityIssueAreaAction requiredStatus
T-075P3Wolf ranges Two complimentary knob sets - Kitchen and SculleryKitchenConfirm Brushed Brass and Red Knob sets. Wolf supplies two complimentary knob sets per range.IN PROGRESS